Karachi Yellow Line BRT: Construction Status, Route & Latest Update 2026

Karachi’s Yellow Line BRT is one of the most awaited public transport projects in the city, and for people living in Korangi and Landhi it could change the daily commute completely. The line is being built as a 21-kilometre dedicated bus corridor from Dawood Chowrangi to Numaish, with World Bank funding behind it. Construction is under way on several sections at the same time, but the service has not started yet, and no passenger has boarded a Yellow Line bus so far.

The project is part of Karachi’s wider BRT network, known as Karachi Breeze, in which the Green Line and Orange Line are already running while the Red Line and Yellow Line are still under construction. When the Yellow Line opens, it will connect the eastern side of the city with the central areas, giving thousands of daily commuters a faster and more reliable way to travel. The World Bank says the system is designed to eventually serve more than 300,000 passengers every day.

Karachi Yellow Line BRT Route: Dawood Chowrangi to Numaish

The Yellow Line starts at Dawood Chowrangi near Quaidabad and runs through Korangi, crossing the Jam Sadiq Bridge and following Main Korangi Road. From there it passes the FTC Interchange and continues along Shahrah-e-Faisal and Shahrah-e-Quaideen, then along Kashmir Road to Numaish Chowrangi in the centre of the city. At Numaish, passengers will be able to change to the Red Line, and the corridor continues through the common BRT corridor towards Tower.

This route matters because it serves some of the most crowded residential and industrial areas of Karachi, including Korangi Industrial Area, Landhi, Shah Faisal Colony and Malir Halt. People from these areas currently rely on crowded minibuses and long, slow journeys to reach Saddar and the city centre. A dedicated BRT corridor with its own lanes should cut that travel time sharply once the buses start running.

Construction Status: What Is Ready and What Is Left

Work on the Yellow Line is moving on several fronts at once. According to project figures reported in August 2026, cumulative funding disbursement had reached Rs31,724.16 million, with spending of Rs19,927.76 million as of 30 July 2026. The Jam Sadiq Bridge package, covering 1.1 kilometres, had reached 56.21 percent completion, with completion targeted for March 2027. The two bus depots are also under construction: Depot-2, spread over 9.25 acres, was about 41 percent complete, while Depot-1, on 2.95 acres, was around 12 percent complete, with an extension of time granted up to 13 November 2026.

In August 2026, Sindh Senior Minister Sharjeel Inam Memon told officials that the depots were expected to be completed in the first quarter of 2027, and he ordered all utility shifting and relocation work to be finished on priority so that construction would not slow down. Then in October 2026 he went further, directing that construction continue around the clock, with special priority for the second section of the Taj Haider Bridge and for the depots. Departments and contractors were told to work under one coordinated plan instead of handling each section separately, with regular monitoring of every package.

The project has also become more expensive over time. The Sindh cabinet approved a revised PC-I worth 620 million dollars earlier this year, and the official completion target attached to that revised plan is 31 December 2028. That is a reminder that the Yellow Line has faced repeated delays since it was first approved by ECNEC in October 2019, and that the new deadlines will only matter if the current pace of work is maintained.

When Will the Yellow Line Open?

According to the project documents, BRT operations are targeted to begin in January 2028, and the fleet of 256 electric buses is planned to start arriving from February 2028. It is important to be clear about this: January 2028 is a reported target, not a confirmed opening date. No official launch date has been announced, and before any passenger service begins, the authorities will still need to finish construction, test the corridor, and complete safety checks. The fare, ticketing system and station facilities have also not been officially announced yet, and no online registration system for regular passengers exists at this stage.

For commuters, the sensible approach is to follow the official announcements rather than the many dates that circulate on social media. If the January 2028 target holds, the Yellow Line will give Korangi and Landhi a direct, modern link to Numaish, Saddar and Tower, and a proper interchange with the Red Line and the rest of the BRT network. Until then, the Green Line BRT remains the running option for travel between Surjani Town and Numaish. We will update this page as soon as the Sindh Mass Transit Authority or the project team announces a confirmed opening date or fare details.